HW1A Binh Thuan maintenance project using CRS-2P - Chip Seal
High-performance Chip Seal application for a major south Vietnam highway project.
The HW1A road in Binh Thuan province showed many cracks in the wearing course under heavy-duty service. The customer decided to use the Chip Seal technique to protect the surface under heavy traffic. CRS-2P, Chip seal emulsion from ADCo, has been applied to maintenance road construction in the BOT Phuong Nam project. KM 1661 + 600 HW1 BINH THUAN province for the area of about 125,000 sqm trial with Tan Ha customer in July 2021. This high-performance CRS-2P provides good bonding between old pavement and new aggregate surfaces as
well as providing a shorter curing time, to waterproof and protect the pavement, safe and simple application with reasonable pricing.
Project name: HW1A Binh Thuan maintenance project using CRS-2P - Chip Seal
Years: 2021
Location: Binh Thuan
Investors: BOT Phuong Nam
Contractors: Tan Ha Investment Co. Ttd
Consultant: Thang Long
Scope of project: 125,000 m2
Construction section: Double layer chip seal